Churches and Steeples

*Indicates properties listed on the National Register

The New Castle Congregational Church, New Castle, NH          2009-10

Structural repairs to historic church including sill repairs and the structural reinforcement of the pulpit wall along the back gable end of the sanctuary.  Work includes the complete restoration of the original bell tower dome removed to the ground and abandoned by cell phone company.

*The Damariscotta Bapstist Church, Damariscotta, Maine 2008-10

Full Frontal

Full Frontal

Since 1846, this steeple has served as a beacon for seamen and travelers along the Maine coastline.  It suffered a fire, probably from lightning damage, in the early 1900s, and suffered from additional water damage in the intervening years.  In 2007, the steeple was removed and carefully tagged, documented and disassembled.  While approximately half of the trim could be repaired, the entire frame required replacement.

One bent of the clock tower frame, being lifted by a crane

A crane lifts one bent of the clock tower frame

The new frame is a twin of the old, aside from adjustments in wood species (Eastern White Pine, or Southern Yellow, to Oak) and lumber dimensions (bed timbers, girts) required by structural carrying capacities.

The assembly of the belfry and spire frame were completed in late August 2009.  During that time, volunteers from the church and community double-primed and sorted each of the fishscale shingles that adorns the spire.  We repaired the pilasters and many of the capitals that decorate the belfry, and reproduced the corner boards, crown molding and about half of the corbels on the spire.  For more information on the repair and reproduction of the trim, see our blog.

Steady Betty

We found extensive water damage in the clock tower frame.  None of the four posts could be saved, and two of the rear posts were dangerously rotten.  Behind the belfry, a new clock tower frame was erected in the side lawn of the church.

In August 2010, we removed the old clock tower and replaced it with the new clock tower and spire.  Our blog posts from that time documented the process, and the media attention it received.  Contact Shawn for more information.

 

Acworth Meetinghouse, Acworth, New Hampshire 2008-2009

This double lantern steeple was built in 1821, by Elias Carter, from Asher Benjamin designs.  It features one of four bells attributed to Paul Revere.  The repairs ran from foundation to steeple and were performed by a committed crew of community craftspeople.  Preservation Timber Framing supervised and planned the complete restoration of  the double lantern dome with center mast, tower box frame and belfry.  White oak, pine and spruce timbers match original fabric.   PTF taught and worked closely with local craftspeople to successfully complete the restoration.  Please contact Arron Sturgis for more information.

The Kennebunkport Baptist Church, Kennebunkport, ME         2009-10

Full assessment of historic church with removed belfry frame and dome.
Work to begin on its full restoration in 2010.

First Parish Church, York, Maine            2009

Structural repair of original belfry and queen post truss roof system.  Supervision of roofing crew and installation of critical flashing elements at junction of steeple and sanctuary roof.  Installation of accessible catwalk and lights within sanctuary roof attic space.  Repair of replacement window sash in sanctuary.

First Universalist Church, Yarmouth, Maine          2006-2008

Yarmouth UU church

Yarmouth UU church

This steeple, erected in 1860, has a simple, eight-sided spire and open belfry.  In 2006, we began the first of a four-phase project by removing the existing spire.

In 2007, phase II included the structural repair of the octagonal belfry.  Five of eight posts were replaced in kind with 40 foot long spruce timbers. The exterior trim on the belfry was repaired and or replaced in kind.

In 2008, we began repair of the spire.  It required complete redesign and replacement of its crab, the overlapping bed timbers at the top of the belfry that support the spire.  By repairing the rafter feet, we were able to restore much of the original spire frame.  This spire was unique, in that its rafters did not telescope deeply into the belfry, which would have provided extra stability, but compromised its airy, open plan.  Careful use of modern tension connectors allowed us to preserve the design, while allowing us to provide additional stability to the spire for many years to come.  Please contact Dave for more information


First Congregational Church of Topsfield, Topsfield, MA          2007

Complete structural restoration of the spire, belfry and belfry box base; including the removal of the spire and belfry and their complete dismantling, repair and re-installation of in kind timber framed structures.  Steel patch work was removed.  All exterior trim was removed, stripped of paint and re-applied in original locations where possible.  Some in kind replacement of exterior trim elements were created to match original fabric.

*First Parish Church of Brunswick, Brunswick, ME          2003

Complete preservation of an historic timber frame bell tower, dated to 1846. Preservation included in kind reproduction of original top sixty feet.

*Pearl of Portsmouth, Portsmouth, New Hampshire          2003

Repaired timber frame belfry, built in 1858. Significance as church of first African American congregation in New Hampshire merited L-CHIP funding. Repair work utilized the original structure to fabricate in kind replacement and reproduction of original architectural elements.

Saint John’s Church, Portsmouth New Hampshire          2001

Structural reinforcement of sanctuary balcony to allow for the installation
of a new pipe organ.  Moved and reinstalled original box pews to allow
room for the organ.  Created and installed a new choir loft riser system
around perimeter of new organ.  Created and installed original and new
matching trim elements in balcony wall to accept organ positive.

First Parish Church of Gorham, Gorham, Maine          2001

Structural repair and reinforcement of king post truss roof system.
Work included in kind timber repair to 60′ truss chords and
reinforcement of tension joinery with steel straps.

Leave a Reply

Your email address will not be published. Required fields are marked *

*

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>